How long should I wait before I can install Quick-Step Parquet on a fresh concrete floor or screed?

Concrete floors or screeds need sufficient time to dry before you can start installing your Quick-Step hard wood floor on top. In case of a glued down installation it is crucial that the moisture content of the screed is within the specified limits. Control measurements using the CM method are strongly recommended. Make sure to take screed over the whole thickness.

For floating installations, the rule of thumb is to wait one and a half weeks per cm of concrete (thickness) up to 6 cm. Wait 4 weeks for every additional cm (thickness) beyond 6 cm.


Concrete floor thickness Advised drying time
<6 cm 1,5 weeks per cm
6 cm 9 weeks
> 7 cm 9 weeks (for the first 6 cm)
+4 weeks per additional cm

For example: for a 7 cm thick concrete floor, you should count on at least (6 x 1.5 week) + (1 x 4 weeks) = 13 weeks of drying time.

Tip: always make sure that the building is sufficiently ventilated.

Learn more:


Was this article helpful?

Thank you for your feedback!

Oops. Something went wrong.

An unknown error has occurred. Please try again. If the issue continues, please get in touch.


Related articles

  • What do I have to do before I start laying my wood floor?
  • Which underfloor should I choose for my hardwood floor?
  • Where to start installing your wood flooring?
  • How to prepare the subfloor for wood flooring?

Find a dealer nearby

Whether you’ve already found the perfect flooring or want to explore some more: our vast network of Quick-Step dealers is always close by.